chore: update work item statuses and daily logs for May 8, 2026, including new daily log entry

This commit is contained in:
2026-05-08 08:09:39 -06:00
parent 1c9b9fd51a
commit 1382f1ac1a
7 changed files with 69 additions and 16 deletions

View File

@@ -2,7 +2,7 @@
type: current
project: fidelity
status: active
updated: 2026-05-05
updated: 2026-05-08
tags:
- current-work
- fidelity
@@ -18,7 +18,8 @@ tags:
- Follow up on active tickets through `project-knowledge/02-work-items/`, especially branch maintenance for `PDIAP-15838` and implementation planning for `PDIAP-15836` / `PDIAP-12284`
- `PDIAP-15765` is done and `PDIAP-14859` is also done
- `PDIAP-15838` is Done from a Jira/status perspective after external review feedback was addressed, but its draft PR must remain unmerged and kept current with `main` until REST backend production readiness and the required REST-toggle consumer validation window allow merge
- `PDIAP-15836` is now paired with `PDIAP-12284` for the UIKit-removal / pure SwiftUI lifecycle implementation path; Quy already moved both into next sprint `26Q2.6`, David can start work now, but leave Jira status in To Do and do not move either story to In Progress until Thursday
- `PDIAP-15836` has moved to In Progress. David found a possible minimal dismissal fix path that would not require removing `UIHostingController`, but Jeff directed David to do the `PDIAP-15836` dismissal/lifecycle work and `PDIAP-12284` UIKit-removal work in the same branch because both are disruptive enough to require consumer testing.
- `PDIAP-12284` remains paired with `PDIAP-15836`; plan the branch as combined UIKit-removal / SwiftUI lifecycle work rather than splitting the dismissal sequencing into an independently merged path unless direction changes.
- Keep the separate `HybridBrokerageAccountOpening` / `JointIdentityCheck` scenario out of `PDIAP-15765` scope unless later evidence proves it belongs there
- Include feature-flag planning for the broader UIKit-removal spike, including dismissal sequencing changes that affect consumers
- Thoroughly verify current `ApexBridgingAddressComponent` / rule-loading usage before describing it as inactive or dead code

View File

@@ -2,7 +2,7 @@
type: current-work-items
project: fidelity
status: active
updated: 2026-05-05
updated: 2026-05-08
tags:
- current-work
- work-item
@@ -24,11 +24,11 @@ Update the per-ticket files first when scope, status, sequencing, or communicati
- `PDIAP-15836` - Modernize dismissal delegate lifecycle sequencing for pure SwiftUI environment
Detail: `project-knowledge/02-work-items/pdiap-15836.md`
Current note: approved at `8` points and now paired with `PDIAP-12284` for the UIKit-removal implementation path. Quy already moved it into next sprint `26Q2.6`; leave it in To Do and do not move to In Progress until Thursday. Treat `PDIAP-15836` as blocked by `PDIAP-12284` unless validation proves the lifecycle fix can be implemented independently.
Current note: moved to In Progress on May 7. David found a possible minimal dismissal fix path that would not require removing `UIHostingController`, but Jeff directed David to do the dismissal/lifecycle work and `PDIAP-12284` UIKit-removal work in the same branch because both changes require consumer testing.
- `PDIAP-12284` - Remove UIKit wrapping from XFlow
Detail: `project-knowledge/02-work-items/pdiap-12284.md`
Current note: reopened after rollback and should be handled with `PDIAP-15836`. Quy already moved it into next sprint `26Q2.6`; work can begin now, but Jira status stays To Do until Thursday and merge/release waits until after REST-transition consumer validation.
Current note: reopened after rollback and should be handled with `PDIAP-15836` in the same branch. Jeff's current direction is to combine the UIKit-removal and dismissal/lifecycle changes because both are disruptive enough to require consumer testing; merge/release still waits until after REST-transition consumer validation.
## Backlog / Future Reference