chore: update work item statuses and daily logs for May 11, 2026, including new daily log entry and adjustments to dismissal sequencing validation
This commit is contained in:
@@ -8,7 +8,7 @@ systems: [xflowsdk, xflowviewmaker, ftframeworks]
|
||||
workstreams: [xflow-swiftui-migration, consumer-integration]
|
||||
people: [jeff-dewitte]
|
||||
related: [pdiap-14859, pdiap-12284, pdiap-15838]
|
||||
updated: 2026-05-08
|
||||
updated: 2026-05-11
|
||||
tags:
|
||||
- work-item
|
||||
- fidelity
|
||||
@@ -22,6 +22,7 @@ tags:
|
||||
- Moved to In Progress on May 7.
|
||||
- David found a possible minimal dismissal fix path that would not require removing `UIHostingController`, and was validating it.
|
||||
- Jeff directed David to do this dismissal/lifecycle work together with `PDIAP-12284` in the same branch because both changes are disruptive enough to require consumer testing.
|
||||
- May 11 simulator log review suggests the tested SwiftUI-host path now fires in the intended order: host-disappearance confirmation precedes `fireEndActivityDelegates`, delegate callbacks, and `activitySession` cleanup. Treat this as promising validation evidence for the tested run, not final consumer validation.
|
||||
- Sequenced after `PDIAP-15838` source work, but merge/release is delayed until after REST-transition consumer validation
|
||||
- Sized at `8` points
|
||||
|
||||
@@ -52,6 +53,7 @@ tags:
|
||||
- It is aligned with epic `26Q2 - Updating XFlowSDK to Decouple and Fix ApexKit Dependencies (Split Part 2)`.
|
||||
- If possible, it should use the same consumer-impact feature flag strategy as the broader UIKit-removal rollout.
|
||||
- Current combined-branch planning should keep dismissal sequencing host-agnostic: the SwiftUI host path must prove dismissal completion before delegate callbacks, while the temporary `UIHostingController` fallback should preserve legacy dismiss-completion behavior.
|
||||
- Current validation logs did not show the key failure patterns for the tested run, such as delegate firing before host-disappearance confirmation or repeated host-disappearance confirmation for the same dismissal id.
|
||||
- Expect a long-lived branch: after implementation, maintain the branch until consumer-testing approval. Jeff expects the GraphQL-removal branch to merge first after the REST validation period, then that branch should be merged into the `PDIAP-15836` / `PDIAP-12284` branch. Current estimate is roughly 90-100 days from 2026-05-05 unless Fidelity shortens the review windows.
|
||||
|
||||
---
|
||||
|
||||