refactor: update work item statuses and sprint planning details for PDIAP-15836 and PDIAP-12284
This commit is contained in:
@@ -24,11 +24,11 @@ Update the per-ticket files first when scope, status, sequencing, or communicati
|
||||
|
||||
- `PDIAP-15836` - Modernize dismissal delegate lifecycle sequencing for pure SwiftUI environment
|
||||
Detail: `project-knowledge/02-work-items/pdiap-15836.md`
|
||||
Current note: approved at `8` points and now paired with `PDIAP-12284` for the UIKit-removal implementation path. Do not move to In Progress until the next sprint starts on Thursday after lunch. Treat `PDIAP-15836` as blocked by `PDIAP-12284` unless validation proves the lifecycle fix can be implemented independently.
|
||||
Current note: approved at `8` points and now paired with `PDIAP-12284` for the UIKit-removal implementation path. Quy already moved it into next sprint `26Q2.6`; leave it in To Do and do not move to In Progress until Thursday. Treat `PDIAP-15836` as blocked by `PDIAP-12284` unless validation proves the lifecycle fix can be implemented independently.
|
||||
|
||||
- `PDIAP-12284` - Remove UIKit wrapping from XFlow
|
||||
Detail: `project-knowledge/02-work-items/pdiap-12284.md`
|
||||
Current note: reopened after rollback and should be handled with `PDIAP-15836`. Work can begin, but Jira status movement waits for the next sprint; merge/release waits until after REST-transition consumer validation.
|
||||
Current note: reopened after rollback and should be handled with `PDIAP-15836`. Quy already moved it into next sprint `26Q2.6`; work can begin now, but Jira status stays To Do until Thursday and merge/release waits until after REST-transition consumer validation.
|
||||
|
||||