type: daily project: fidelity date: 2026-04-20 status: active focus: [rest-migration] work-items: [pdiap-15838] blockers: [] tags: - daily - fidelity updated: 2026-04-20

2026-04-20

Focus

  • Prioritize investigation into why REST is not activating on iOS.
  • Continue PDIAP-15838 with the investigation as the immediate focus.

Work Done

  • Moved PDIAP-15765 to Done.
  • Moved PDIAP-14859 to Done.
  • Updated PDIAP-15838 to In Progress.

Findings

  • The immediate priority is no longer closeout work on the completed stories.
  • The immediate priority is to investigate why REST is not activating.
  • David clarified additional Fidelity-side process context: Quy acts as Scrum Master, manages retrospectives, DSE/daily syncs, sprint review, and sprint planning, retrospectives use Miro, Jira is the tracking system, and the Fidelity-side sprint cadence is two weeks with labels like PDIAP 26Q1.1 and PDIAP 26Q2.1.
  • David corrected the Q2 sprint examples: PDIAP 26Q2.1 is 3/26 - 4/09, and PDIAP 26Q2.2 is 4/09 - 4/23.
  • David clarified that Jira should be represented as a first-class Fidelity tool/system because it is used more heavily than Confluence in day-to-day work tracking.

Communication


Next Steps

  • Investigate why REST is not activating on iOS.
  • Continue PDIAP-15838 from that investigation path.

Blockers

  • None currently.